Jack Wrote:Interesting.............in which year did you invent this? I'm only asking because I have seen this methodology on at least five projects going back as far as 2003.
twas last century - on a pipeline on which no other evaluation was undertaken - after the first brand new Roman site was revealed, the engineers were shocked at the delay so a continuous eval trench down the middle enabled some mitigation and easement narrowing when the next ones appeared
never ideal but better than nowt