Not a bad report in many respects- but......
The ought be of the order of 396 evaluation trenches dug which can only take place once the ecology is completed so I would have expected a mention of this is the following section of the report
"5.5.5 Programming issues/ planning/ development plan key stages
Given the nature and scale of the indicative development there are likely to be several key programming issues
that should be highlighted.
1. Early consultation with statutory bodies particularly over the Harmondsworth Barn, listed building
demolition, and demolition within conservation areas and setting of listed building and conservation areas
will be important.
2. Determine as soon as practicable what consents will be required and plan submission programme.
3. Ensure historic environment constraints are thoroughly integrated with any scheme design work to
optimise potential for design to mitigate any adverse effects.
4. Ensure negotiation for sites for relocation / storage of buildings (if required) is completed as soon as
reasonably practicable"
Peter
The ought be of the order of 396 evaluation trenches dug which can only take place once the ecology is completed so I would have expected a mention of this is the following section of the report
"5.5.5 Programming issues/ planning/ development plan key stages
Given the nature and scale of the indicative development there are likely to be several key programming issues
that should be highlighted.
1. Early consultation with statutory bodies particularly over the Harmondsworth Barn, listed building
demolition, and demolition within conservation areas and setting of listed building and conservation areas
will be important.
2. Determine as soon as practicable what consents will be required and plan submission programme.
3. Ensure historic environment constraints are thoroughly integrated with any scheme design work to
optimise potential for design to mitigate any adverse effects.
4. Ensure negotiation for sites for relocation / storage of buildings (if required) is completed as soon as
reasonably practicable"
Peter