10th March 2006, 02:18 PM
Here's an interesting story from the CBA website. It's highlights a couple of problems my company encounters often. That for watching briefs of uncertain duration it is difficult to estimate post ex costs, and that developers are quite often happy to pay for the site work, but then do everything to avoid paying for a proper report. One wonders why the planning condition was signed off without it.
Site owner told to pay archaeologist ?8,470
Thursday March 9th 2006
The site on which the Browne Street Bar is built, and its archaeological significance, was at the centre of a civil case in Carlow Circuit Court.
An old quarry that supplied the stone that was used to build Carlow and an ancient ditch that bordered the town were found on the corner of Browne Street and College Street.
The court heard that the owner of the site, Peter McCormack, 50 Tullow Street, Carlow, was granted planning permission to build on it in May, 2003, on the condition that he employed an archaelogist to supervise, record and report on the findings of an excavation dig.
Mr. McCormack was the defendant in the case, brought against him by consultant archaeologist, Mr. Patrick Neary, 24 Talbot's Inch, Kilkenny. He sued Mr. McCormack for the cost of writing a detailed and mandatory report on the dig's findings to the sum of ?8,470.
In his evidence in court, Mr. Neary said that both men agreed that his fee should be ?350 per day on the site and that he was paid on a weekly basis, promptly, by Mr. McCormack. However, when the dig was completed, and Mr. Neary wrote up the report, Mr. McCormack refused to pay the cost incurred in writing it up. Mr. Neary also said that the excavation was particularly difficult because it was so deep and that he used photographs to record his findings for health and safety reasons. Using photographs also meant that he wouldn't delay the progress of the site unduly.
He added that, in writing up the report, he had to sort through over 1,000 photographs and that his findings had to be re-interpreted for a surveyor. It took him 20 days to complete the report.
Judge Michael O'Shea heard that when the report was almost completed, Mr. Neary rang Mr. McCormack to tell him it was almost ready, but that Mr. McCormack refused to pay him. Mr. Neary said that he wouldn't give him the document until it was paid for.
Counsel for the defence, Elaine Morgan, BL, put it to Mr. Neary that archaeologists usually get paid a daily site allowance and that this fee would cover the cost of any reports. Mr. Neary refuted this, saying that this was 'never the case.'
Peter McCormack gave evidence, saying that he was a Chartered Accountant and Auditor. He said that he thought that the ?350 daily site fee included the cost of writing up the report. He also said that he was surprised when Mr. Neary rang him to tell him that the report was almost completed and that it cost 'in excess of ?5,000.' He said that Mr. Neary hadn't mentioned the additional cost of writing the report previously in their business transaction.
A civil engineer, Pat Buckley, gave evidence for the defence, saying that developers would usually get quotations in advance of a job so that they could budget the costs. However, he said that it would be difficult for an archaeologist to give an advanced quotation, given that they wouldn't yet know the extent of the project. He added that he didn't have direct experience of archaeologists being paid daily site fees.
Finding in favour of the plaintiff, Judge Michael O'Shea said that Peter McCormack seemed like a 'decent' man, but that the archaeological report was 'extremely important' and that it was a mandatory part of the project. He also said that Mr. Neary should be paid for work done under services rendered and ordered Mr. McCormack to pay the cost of the report, which was ?8,470.
? Carlow Peoplehttp://www.unison.ie/carlow_people/ & http://www.unison.ie/
Site owner told to pay archaeologist ?8,470
Thursday March 9th 2006
The site on which the Browne Street Bar is built, and its archaeological significance, was at the centre of a civil case in Carlow Circuit Court.
An old quarry that supplied the stone that was used to build Carlow and an ancient ditch that bordered the town were found on the corner of Browne Street and College Street.
The court heard that the owner of the site, Peter McCormack, 50 Tullow Street, Carlow, was granted planning permission to build on it in May, 2003, on the condition that he employed an archaelogist to supervise, record and report on the findings of an excavation dig.
Mr. McCormack was the defendant in the case, brought against him by consultant archaeologist, Mr. Patrick Neary, 24 Talbot's Inch, Kilkenny. He sued Mr. McCormack for the cost of writing a detailed and mandatory report on the dig's findings to the sum of ?8,470.
In his evidence in court, Mr. Neary said that both men agreed that his fee should be ?350 per day on the site and that he was paid on a weekly basis, promptly, by Mr. McCormack. However, when the dig was completed, and Mr. Neary wrote up the report, Mr. McCormack refused to pay the cost incurred in writing it up. Mr. Neary also said that the excavation was particularly difficult because it was so deep and that he used photographs to record his findings for health and safety reasons. Using photographs also meant that he wouldn't delay the progress of the site unduly.
He added that, in writing up the report, he had to sort through over 1,000 photographs and that his findings had to be re-interpreted for a surveyor. It took him 20 days to complete the report.
Judge Michael O'Shea heard that when the report was almost completed, Mr. Neary rang Mr. McCormack to tell him it was almost ready, but that Mr. McCormack refused to pay him. Mr. Neary said that he wouldn't give him the document until it was paid for.
Counsel for the defence, Elaine Morgan, BL, put it to Mr. Neary that archaeologists usually get paid a daily site allowance and that this fee would cover the cost of any reports. Mr. Neary refuted this, saying that this was 'never the case.'
Peter McCormack gave evidence, saying that he was a Chartered Accountant and Auditor. He said that he thought that the ?350 daily site fee included the cost of writing up the report. He also said that he was surprised when Mr. Neary rang him to tell him that the report was almost completed and that it cost 'in excess of ?5,000.' He said that Mr. Neary hadn't mentioned the additional cost of writing the report previously in their business transaction.
A civil engineer, Pat Buckley, gave evidence for the defence, saying that developers would usually get quotations in advance of a job so that they could budget the costs. However, he said that it would be difficult for an archaeologist to give an advanced quotation, given that they wouldn't yet know the extent of the project. He added that he didn't have direct experience of archaeologists being paid daily site fees.
Finding in favour of the plaintiff, Judge Michael O'Shea said that Peter McCormack seemed like a 'decent' man, but that the archaeological report was 'extremely important' and that it was a mandatory part of the project. He also said that Mr. Neary should be paid for work done under services rendered and ordered Mr. McCormack to pay the cost of the report, which was ?8,470.
? Carlow Peoplehttp://www.unison.ie/carlow_people/ & http://www.unison.ie/