CDM applies if the 'construction' phase is likely to involve more than 30 days or 500 person days of construction work. Numbers of personnel and the length of the project are irrelevant. (CDM 2007, Interpretation, Section 2-(3))
Sith, is this interpreted as the time taken from the beginning of a project to it's completion or does it apply (in our case) to the archaeological work only?